2025 Street & Utility Project
Linn Drive SW/Oakdale Street SW
The 2025 Street & Utility Project was awarded to Wencl Construction, and the project will begin with pavement removals on May 5th. The contractor plans to begin at the Linn Drive/18th Street SW intersection and work towards the south around the loop. Any access restrictions will be communicated by the contractor.
Week of May 5th: Please have all vehicles off of the street by 6 am on May 5th. The contractor will begin with removals, reclaiming and setting temporary water. This portion of the project is expected to take about 3 days. Also to take place next week on Linn Drive, Owatonna Public Utilities will have a contractor in to relocate gas lines along the project limits.
Weeks of May 12th - May 19th: Following pavement removal, the contractor will move on to the removal and replacement of underground sanitary sewer and water infrastructure.
Planned work is weather dependent and dates are subject to change.
Property owners have received a driveway information request form, please complete and return the form to the Public Works Office by May 13th.
If you have not already signed up for and would like to receive these weekly updates, visit Notify Me.
2025 Street & Utility Project Map.
Vine Street Parking Lot
The reconstruction of the Vine Street Parking Lot began in the fall of 2024 and a few items were left to complete this spring. Wencl Construction and their subcontractors will begin working on these items in the coming weeks.
The paving contractor anticipates beginning on May 19 to finish paving and permanently striping the lot. This will result in a closure of the entire lot for several days, which may not all be consecutive. Notifications regarding the lot closure will be sent via Notify Me - Vine Street Parking Lot Closures. Motorists who frequent the lot are encouraged to sign up for these notifications. Paving and striping are weather dependent, and dates may shift due to the forecast and current conditions.
2025 18th Street SE Trail Extension
A Pedestrian and Bicycle Trail running along the South side of 18th Street SW and the North side of 18th Street SE is planned for construction in 2025. The project has been awarded to Ulland Brothers and is expected to begin June 4th. The contractor plans to begin at the intersection of 18th Street SE and Austin Road and work towards the west.
18th Street SE Trail Extension Map
Cured in Place Pipe Systems (CIPPS) Project
Work on the CIPPS Project has been ongoing since mid-March. The contractor, HydroKlean, has completed all precleaning and televising and has moved on to the lining process.
Next week the planned lining areas include:
- Pylor Place NW
- Glendale Street NW
- 7th Avenue NE
- Prospect Street SE