2025 Street & Utility Project
Linn Drive SW/Oakdale Street SW
May 23 Recap: On Monday, the contractor finished work on the replacement of the sanitary sewer main on Linn Drive. No work was completed on Tuesday, Wednesday or Thursday due to the weather. Thank you for your patience throughout the rainy, muddy week. Reclaimed bituminous material has been left on Oakdale to help with accessibility to residents in the area.
Work will begin on May 23rd to replace watermains at the intersection of 18th Street and Linn Drive, moving south. This is estimated to take a full week to complete. Crews will not be working on Monday May 26 in observance of Memorial Day.
Upcoming Plans: Following completion of the watermain, work will begin on the storm sewer infrastructure. The contractor plans to begin work on Oakdale the week of June 9th.
Planned work is weather dependent and dates are subject to change. Any access restrictions will be communicated by the contractor.
If you have not already signed up for and would like to receive these weekly updates, visit Notify Me.
2025 Street & Utility Project Map.
Vine Street Parking Lot
The paving contractor anticipates beginning on May 29 to finish paving and permanently striping the lot. This will result in a closure of the entire lot from May 29th to June 3rd. Paving and striping are weather dependent, and dates may shift due to the forecast and current conditions. Please note: These dates have been updated since the publication of the May 21 Owatonna Update.
Notifications regarding the lot closure will be sent via Notify Me - Vine Street Parking Lot Closures. Motorists who frequent the lot are encouraged to sign up for these notifications. Paving and striping are weather dependent, and dates may shift due to the forecast and current conditions.
2025 18th Street SE Trail Extension
A Pedestrian and Bicycle Trail running along the South side of 18th Street SW and the North side of 18th Street SE is planned for construction in 2025. Ulland Brothers will begin bringing in structures on May 27th with work scheduled to begin on June 2nd. Structures will be stored near the Fairgrounds Softball Fields. The roadway will remain open, please slow down and use caution when in the area.
Cured in Place Pipe Systems (CIPPS) Project
Work on the CIPPS Project has been ongoing since mid-March. The contractor, Hydro-Klean, has completed all precleaning and televising and has moved on to the lining process. Affected property owners will receive door knockers prior to the lining. Any questions or concerns related to the work should be directed to Hydro-Klean at 1-855-845-5326.
View the interactive project map to see where work will be taking place this season: Engineering Project Map | Owatonna, MN.