2025 Street & Utility Project
Linn Drive SW/Oakdale Street SW
The 2025 Street & Utility Project was awarded to Wencl Construction. Planned work is weather dependent and dates are subject to change. Any access restrictions will be communicated by the contractor.
Week of May 30 Recap: The contractor is continuing to work on running watermain on Linn Drive. They have connected new sanitary and water services to homes North of Oakdale, on Linn Dr, and have begun sub-cutting in the area to put down base materials for the roadway.
Upcoming Plans: The contractor will work on connecting the rest of the sanitary and water services on Linn Dr. They will then move onto storm improvements along Linn, followed by sub-cutting and base material placement. After Linn is filled with base materials, they will begin construction of underground utilities and roadway surface on Oakdale. The contractor plans to begin work on Oakdale the week of June 9th, weather permitting.
In the event of heavy rainfall residents are encouraged to park on the north end of 2nd off of Oakdale or on the south side of 18th Street SW. Thank you for your patience and cooperation as we understand the wet weather has caused a bit of inconvenience.
If you have not already signed up for and would like to receive these weekly updates, visit Notify Me.
2025 Street & Utility Project Map.
Vine Street Parking Lot
The paving contractor began removals, paving and permanently striping the lot on May 30. The lot is currently closed and will remain closed until June 3.
Notifications regarding the lot closure will be sent via Notify Me - Vine Street Parking Lot Closures. Motorists who frequent the lot are encouraged to sign up for these notifications. Paving and striping are weather dependent, and dates may shift due to the forecast and current conditions.
2025 18th Street SE Trail Extension
Ulland Brothers will begin construction on a Pedestrian and Bicycle Trail running along the South side of 18th Street SW and the North side of 18th Street SE on June 2nd. They will begin by installing a stormwater underground filtration system near the intersection of Austin Road and 18th Street SE and work their way to the west. 18th Street will remain open to vehicle traffic. Drivers should slow down and use additional caution when in the area.
18th Street SE Trail Extension Map
Overlay Prep Project
1.56 miles of roadway will be overlayed by the Owatonna Street Department in 2025. Steve James Excavating will begin replacing and adjusting manhole and catch basin castings/structures in preparation of the paving to take place this summer. They plan to begin prep work in the next few weeks, and it is expected to take approximately one week to complete. Please use caution when approaching the work area.
The work areas can be seen highlighted in red on this map.
View the interactive project map to see where work will be taking place this season: Engineering Project Map | Owatonna, MN.