2025 Street & Utility Project
Linn Drive SW/Oakdale Street SW
The 2025 Street & Utility Project was awarded to Wencl Construction. Planned work is weather dependent and dates are subject to change. Any access restrictions will be communicated by the contractor.
Weekly Recap: Wencl continued with watermain and sanitary services on the West leg of Linn, from Oakdale heading south.
Upcoming Plans: Subcutting has begun on the East leg of Linn heading approximately 300 ft south and then base materials will go down in that area. This should supply some reprieve to more residents as far as access and road drivability. They plan to continue south with sub cutting and base materials to further this accessibility as quickly as possible. We appreciate the residents’ patience with the weather and less than desirable conditions caused by that.
2025 Street & Utility Project Map.
2025 18th Street SE Trail Extension
Ulland Brothers began construction on a Pedestrian and Bicycle Trail running along the South side of 18th Street SW and the North side of 18th Street SE on June 2nd.
Weekly Recap: Work this week involved preparation for the installation of the underground stormwater system and the same nature of work is expected to continue next week.
18th Street SE Trail Extension Map
Wastewater Treatment Facility
Retaining Wall Project
The existing retaining wall on the northeast side of the Wastewater Treatment Facility (WWTF) will be replaced with a Reinforced Soil Slope (RSS) wall. The design grade for the WWTF site requires either the existing retaining wall height to be increased or it needs to be replaced with a new system that accommodates the change in grade. The existing wall shows evidence of distress and adding height to the wall is not advised. An RSS wall is recommended as it is the most cost-effective option and causes the least disturbance to existing utilities.
Construction of the replacement wall is scheduled to begin on July 7th and will result in the closure of the North Straight River Trail for 6 to 8 weeks. An update and confirmation of the construction start date will be provided as the anticipated start date approaches.
Vine Street Parking Lot
Miscellaneous items for the Vine Street Parking Lot will be completed in the following weeks to close out the project.
2025 CIPPS
Work on the CIPPS Project has been ongoing since mid-March. The contractor, Hydro-Klean, has completed all precleaning and televising and has moved on to the lining process. Affected property owners will receive door knockers prior to the lining. Any questions or concerns related to the work should be directed to Hydro-Klean at 1-855-845-5326. The project is nearing completion with only a few segments left.
2025 Overlay
1.56 miles of roadway will be overlayed by the Owatonna Street Department in 2025. Steve James Excavating will begin replacing and adjusting manhole and catch basin castings/structures in preparation of the paving to take place this summer.
They plan to begin prep work in the next few weeks, and it is expected to take approximately one week to complete. Please use caution when approaching the work area.
The work areas can be seen highlighted in red on this map.
View the interactive project map to see where work will be taking place this season: Engineering Project Map | Owatonna, MN.