2025 Street & Utility ProjectLinn Drive SW/Oakdale Street SWThe 2025 Street & Utility Project was awarded to Wencl Construction. Planned work is weather dependent and dates are subject to change. Any access restrictions will be communicated by the contractor. Weekly Recap: The week of June 30th, crews are finishing up the storm sewers. 2025 Street & Utility Project Map. 2025 18th Street SE Trail ExtensionUlland Brothers began construction on a Pedestrian and Bicycle Trail running along the South side of 18th Street SW and the North side of 18th Street SE on June 2nd. Upcoming Plans: The week of July 7, crews will be paving pedestrian ramps. The crews will be removing the black top by the park and moving west towards cedar. 18th Street SE Trail Extension Map
View the interactive project map to see where work will be taking place this season: Engineering Project Map | Owatonna, MN. 2025 OverlayWeekly Recap: The week of June 30th, Minekahda Pl NE milling was completed Upcoming Plans: The week of July 15th, milling will begin on Oakwood Lane from Rose St to Crestview, and then Crestwood from Greenhaven Ln to Dane Rd. Milling takes up to two days. Paving will then begin.
|