How long will a project take?

It depends on the project parameters but typically:

  • Mill and Overlay projects typically take 2 to 6 weeks
  • Rehabilitation projects (full pavement replacement, keeping existing curb and gutter) typically take 6 to 10 weeks
  • Rehabilitation projects (new pavement and curb/gutter construction on existing grade and gravel) typically takes 6 to 8 weeks
  • Full reconstruction projects (with curb and gutter) typically take 8 to 16 weeks